Island Crest Way Corridor Improvements

Project ID: 
22-38 (SP0135)
Project Type:
Street
Project Status: 
Planning/Design

SP0135 Project LocationProject Details/Neighborhood 

Island Crest Way from 90th Ave SE to SE 68th Street 

​Background

A number of traffic safety and operation concerns were identified as part of the Island Crest Way Corridor Safety Analysis in 2022. The next phase of the project aims to address a number of these deficiencies and plan for future projects. 

 

Description

This project includes planning and development of roadway improvements along a one-mile segment of Island Crest Way, including a street lighting study, shared-use path pre-design (analysis of constraints and development of options/alternatives), multiple crosswalk improvements (design and construction), design feasibility study (reconfigurations including a roundabout at SE 68th Street and right turn lane at SE 53rd Place), tree condition assessment (evaluation of all trees in the right-of-way to study health, risks, and maintaining the street tree canopy). The shared use path pre-design will evaluate paths on both sides of Island Crest Way and present the results to the City Council. The feasibility study, analyses, and pre-design efforts will likely result in additional future capital project proposals. City staff will seek viable grant opportunities as the project proceeds.

Project Timeline

Budgeted (Q2 of 2022)
Planning/Design (Q2 of 2023 – Q3 of 2024)
Under Construction (Q2 -Q3 of 2024)
Completed (Q4 of 2024)

 

Project Budget

$1.6 million

Contact

Patrick Yamashita, City Engineer: 206-275-7722 or patrick.yamashita@mercerisland.gov

https://letstalk.mercergov.org/island-crest-way-corridor-improvements-an...

 

 

 

 
Status Updates

November 2023 Update
The City launched a new Let's Talk page to share updates about this capital project. All information will now be shared on Let's Talk, and this CIP project page will no longer be updated. Find project details, key dates, progress updates, and more at: https://letstalk.mercergov.org/island-crest-way-corridor-improvements-analysis-and-design

Week of April 24, 2023 Update

Over the next few months, a survey of the corridor will take place to gather information that will guide the analysis and design process. The community can expect to see crews along the corridor while the survey process is completed.

April 2023 Update- Planning/Design

A consultant team including KPG Psomas, DKS Associates, and Land Meets Water were selected in January 2023 to complete the project design and analysis.

 