SE 80th Street, from 84th Avenue SE to SE 82nd Street
SE 82nd Street, from 84th Avenue SE to SE 80th Street
78th Avenue SE, from SE 76th Street approximately 200 feet south
93rd Avenue SE, from SE 70th Place approximately 300 feet south
The intersection of 80th Avenue SE and SE 28th Street
Background
This annual program repairs and resurfaces residential streets through hot mix asphalt (HMA) overlays. Minor storm drainage repairs and minor water improvements will also be constructed in advance of the resurfacing. Utility work will be funded from the corresponding utility funds.
Project Description
The residential streets of SE 80th and SE 82nd Streets in the neighborhood of Island Point and portions 78th and 93rd Avenues are planned for repaving. Also the intersection of 80th Avenue SE and SE 28th Street in the Town Center will receive an asphalt grind and overlay. These roadway PCI ratings are in the Fair to Very Poor range.
Project Timeline
Planning/Design (Q1 of 2026 – Q2 of 2026)
Construction Timeframe (Q3 of 2026 – Q4 of 2026)
CM Designed was hired in December 2025. Design was completed in May 2026, the project was awarded to Lakeside Industries in June 2026 and construction is estimated to begin in July 2026.